Buckland Estate: power you can count on for the big day

A wedding venue can’t afford a blackout. We rewired the estate and gave it solar, a battery and a 220 kVA generator, with the grid kept for emergencies, so the power stays on when it matters most.

Elevated view of solar panels on two roof sections of a farm building.
Elevated view of solar panels on two roof sections of a farm building.
LocationBuckland, Avon Valley (near Northam), WA
CustomerBuckland Estate, a wedding venue and rural estate with a homestead, workshop, barns, a granary and silo, caravan sites and event spaces
SystemAbout 98.3 kW of rooftop solar (207 × 475 W panels), 200.6 kWh of battery storage and a 220 kVA Genesys/Blue Diamond GEN220CT generator with changeover. The system runs off-grid when carrying the loads, and the existing 2-phase grid connection is kept so that in an emergency the system can be isolated and grid power run through.
EquipmentTongwei 475 W panels, 2 × SAJ CHS2 50 kW inverters with a 100.3 kWh battery each, 2 × 50 kVA inverters (about 200 kVA of inverter capacity in total), Elekeeper monitoring, 220 kVA Genesys/Blue Diamond GEN220CT generator
InstalledAugust 2026 · monitoring handed over October 2026

Gallery

On site at Buckland

The challenge

One day to get right, and a supply that couldn’t keep up

Buckland Estate is a wedding venue. When a couple has one day to get right, the lights, the music, the kitchen and the bar can’t drop out halfway through the speeches. For the owner, power reliability was the top priority, for his business and for the special days his guests share at the estate.

The property didn’t make that easy. It had a 2-phase grid supply that was already supply constrained, on a big rural site with a house, workshop, barns, granary and silo, caravan sites and event spaces, and more cabins and caravan sites planned. The existing switchboards also needed work to bring them up to standard.

What we did

More than one way to keep the power on

The objective was to create a robust, reliable microgrid that used parts of the existing infrastructure, upgrading and improving it where required. The end result: three different potential sources of power, so the site has the utmost reliability. We started with a detailed site investigation and audit to understand the problems and constraints on site. With that information, we worked through several design iterations to optimise and refine the design into the best possible outcome for the client.

  • A new heart for the site: We rewired the property from a new, central main switchboard location, and replaced and upgraded every switchboard to current standards.
  • Three-phase underground: New underground three-phase runs to the main house, the workshop, the new powered van sites and a pillar ready for a future cabin.
  • Solar and battery: 207 Tongwei 475 W panels (about 98.3 kW), 2 × SAJ CHS2 50 kW inverters, each with a 100.3 kWh battery (200.6 kWh of storage in total), plus 2 × 50 kVA inverters, for about 200 kVA of inverter capacity in total.
  • Solar and generator, alone or together: A 220 kVA Genesys/Blue Diamond GEN220CT generator with changeover. The solar and generator can run independently or together, depending on the loads they need to handle. In extreme cases the two can be stacked to create extra capacity on site.
  • Off-grid, with the grid kept for emergencies: The estate runs off-grid when the system is carrying the loads. We retained the existing 2-phase grid connection, and in an emergency the system can be isolated so grid power runs through to the site.
  • Built for what’s next: The infrastructure, designs and connecting infrastructure were all sized for potential future expansion without over-capitalising on labour and materials, leaving headroom for future increases and system expansion.
  • Estate works & handover: Workshop outlets, RGB floodlighting on the workshop, silo, barn and granary, chandelier barn power and lighting, and caravan power via four pillars with 12 outlets. Elekeeper monitoring handed over in person in October 2026.

Delivery was scheduled and managed around the client’s operating schedule. The estate kept trading throughout, with no loss of revenue while the system was being installed.

Project package

Equipment and electrical scope

CategoryEquipmentQtyTotal
Solar panelsTongwei 475 W20798.325 kW
Battery invertersSAJ CHS2 50 kW all-in-one cabinets2100 kW
Additional invertersSAJ R6 50 kVA inverters2100 kVA
Total inverter capacityCHS2 cabinets plus additional inverters–about 200 kVA
Battery100.3 kWh per CHS2 cabinet2200.6 kWh
Generator / backupGenesys/Blue Diamond GEN220CT 220 kVA generator with changeover1220 kVA
GridExisting 2-phase grid supply (retained)–Retained; system can be isolated in an emergency so grid power runs through
MountingS-5! mounting on Trimdek roofs––
MonitoringElekeeper app–Handed over Oct 2026

Electrical scope

  • Detailed site investigation and audit of problems and constraints, then several design iterations
  • Property rewired from a new, central main switchboard location
  • Every switchboard on the property replaced or rectified, fixing non-compliance found
  • New underground three-phase runs to the main house, workshop, new powered van sites and a pillar for a future cabin
  • Generator changeover: generator alone, generator with solar assisting (generator grid-forming), or both stacked for extra capacity
  • Existing 2-phase grid connection retained, so in an emergency the system can be isolated and grid power run through
  • Caravan power: four distribution pillars with 12 outlets, including trenching, concrete and reinstatement
  • Workshop outlets, RGB floodlighting (workshop, silo, barn, granary), chandelier barn power and lighting, tree area and corner posts
  • Infrastructure sized for future expansion without over-capitalising
  • Commissioning, owner walkthrough and Elekeeper monitoring handover (October 2026)

No pricing shown.

The results

Power the venue can count on

No power billsince switch-on (reported result to date, this site)
Generator not neededthe backup generator hasn’t had to run for power to date
Three power sourcessolar and battery, a 220 kVA Genesys/Blue Diamond GEN220CT generator, and the grid, which can be run straight through in an emergency
Renewables firstdesigned to run mainly on solar and battery
Ready to growsized with headroom for future expansion

Results to date, this site: since switch-on the client has had no power bill, and the backup generator has not been needed to provide power to date, as reported by National Renewable in October 2026. These are not guarantees; results depend on weather, site usage and how the system is operated.

Take it with you

Download the case study (PDF)

A print-ready A4 summary, with project photos, of the Buckland Estate project. Every copy, printed or shared, carries a QR code that links back to this page.

PDF · 5 pages · A4 · includes project photos

QR code to this page

nationalrenewable.com.au/projects/buckland-estate

QR encodes the page URL + ?utm_source=qr&utm_medium=print&utm_campaign=case-study so scans show up in Google Analytics.

Related projects

More projects across WA

Drone view of the shopping centre roof with solar arrays and the car park
Drone view of the shopping centre roof with solar arrays and the car park
In progress
Business

Kardinya Park Shopping Centre

Kardinya · Perth metro

In progress: about 1 MW of rooftop solar on the main centre, plus a separate 161 kW system on the Medical Centre, with a 1.78 MWh Deye battery, being installed behind the meter. PV and Medical Centre complete; inverters, battery and switchboards to come.

SolarBattery
IN PROGRESS · PV and Medical Centre complete

Started August 2026

Finished rooftop solar array on a transportable building, with another solar-roofed building and open paddock behind.
Finished rooftop solar array on a transportable building, with another solar-roofed building and open paddock behind.
★ Case study
Business

Balco Hay

Wannamal WA · North of Perth

Off-grid solar and battery microgrid for site accommodation at one of Balco’s production facilities: 48.45 kW of solar, 125 kW of inverters and a 100.3 kWh battery, added alongside the existing systems.

Off-gridSolarBattery
Installed in a single week, May 2026

May 2026

Rows of ground-mounted solar arrays on a grassy hillside, with a steel cable tray in the foreground.
Rows of ground-mounted solar arrays on a grassy hillside, with a steel cable tray in the foreground.
★ Case study
Business

Wise Winery

Eagle Bay, near Dunsborough · South West

About 258 kW of new solar and about 282 kWh of usable battery: a ground mount and rooftop array at the main winery, plus off-grid systems for the back shed and Wise Winery House.

SolarBatteryOff-grid
About 85% self-sufficient in August 2026 (main winery site)

April 2026

Running a venue, farm or rural property?

When the power can’t fail, you need more than one way to keep it on. We design systems that handle real rural loads, from workshops and lighting to caravans and events.